Float, the critical path and the value of network analysis

  • 5 things to know
  • Papers 1, 2 and 3
Start revising · £5/month

Overview

Calculating total float, identifying the critical path, and what network analysis is used for.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Numbers

What is total float, and how is it calculated?

Numbers

What is total float, what happens when an activity with float is delayed, and how does network analysis track progress?

Numbers

What are network diagrams for, what is the critical path, and how is it identified?

Evaluation

When is total float calculated, and how does structure affect implementation?

Numbers

State the formula for calculating total float.

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is the float value for activities on the critical path, and what does this mean?

    Model answer

    Activities on the critical path have zero float, meaning any delay to these activities will delay the entire project.

  2. 2

    Define total float in the context of network analysis.

    Model answer

    Total float is the amount of time an activity can be delayed without delaying the overall project completion date.

  3. 3

    State the formula for calculating total float.

    Model answer

    Total Float = Latest Start Time − Earliest Start Time (or Latest Finish Time − Earliest Finish Time).

  4. 4

    What do the terms 'earliest start time' and 'latest start time' mean in the total float formula?

    Model answer

    Earliest start time is the soonest an activity can begin based on predecessor completion; latest start time is the latest it can begin without delaying the project.

  5. 5

    Calculate the total float when earliest start time = 46 days, latest start time = 52 days.

    Model answer

    Total float = 52 - 46 = 6 days.

  6. 6

    Why is identifying the critical path valuable for managers during strategic implementation?

    Model answer

    It allows managers to focus resources and attention on activities where delays would be most damaging to project completion.

Other ways to work this

The same content, four other ways.

Everything in your subscription

Runs, plus a mode for every other kind of session.

1Flash
2Imposter
3Fade
4Brain dump

Learn every subtopic in runs of four questions

Facts flash and fade, a wrong word hides in some of them, and a brain dump decides which questions are locked in.

What Is Business?
Managers, Leadership and Decision Making
Marketing Management
Operational Management

Cram the night before, weakest topic first

A quick scan finds your weakest topics. Recall each fact you missed three times in a row.

Profit = Revenue − Costs.
TotalFixedVariable

Blank Blitz consolidates the facts

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

✓What it iscovered
~Why it happenspartly there
How long it lastsnot there yet

Explain It tests your understanding

Explain a concept in your own words and see which of its points you covered.

A merger is where businesses agree to combine.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The faults are the mistakes students make most often.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Managing Strategic Change, on a schedule.

Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.