Network diagrams, earliest start and latest finish times, total float, and identifying the path that decides the length of a project.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What is Critical Path Analysis, and what is the critical path?

Numbers

What is the earliest start time, and what happens if the critical path slips?

Numbers

What is total float, and how is it calculated?

Key term

What aspect of project performance does CPA fail to measure?

Key term

What financial aspect of project management is not directly addressed by CPA?

Numbers

State the total-float formula.

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is Critical Path Analysis (CPA)?

    Model answer

    A project management technique that identifies the sequence of dependent activities and calculates the minimum time needed to complete a project.

  2. 2

    What is the purpose of Critical Path Analysis?

    Model answer

    To identify which activities are critical to completing the project on time and where resources can be allocated most effectively.

  3. 3

    What is a network diagram in the context of CPA?

    Model answer

    A diagram that represents project activities as nodes or arrows showing their sequence and dependencies.

  4. 4

    What is the critical path in a network diagram?

    Model answer

    The longest route through the network diagram, which determines the minimum project duration.

  5. 5

    How much float do activities on the critical path have?

    Model answer

    Zero float.

  6. 6

    What happens if an activity on the critical path is delayed?

    Model answer

    The entire project will be delayed.

Other ways to work this

The same content, four other ways.

Everything in your subscription

Runs, plus a mode for every other kind of session.

1Flash
2Imposter
3Fade
4Brain dump

Learn every subtopic in runs of four questions

Facts flash and fade, a wrong word hides in some of them, and a brain dump decides which questions are locked in.

Meeting Customer Needs
The Market
Marketing Mix and Strategy
Managing People

Cram the night before, weakest topic first

A quick scan finds your weakest topics. Recall each fact you missed three times in a row.

Net gain = − initial cost.
EMVNPVARR

Blank Blitz consolidates the facts

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

✓What it iscovered
~Why it happenspartly there
How long it lastsnot there yet

Explain It tests your understanding

Explain a concept in your own words and see which of its points you covered.

Tariff means a tax imposed on imported goods.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The faults are the mistakes students make most often.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Decision-Making Techniques, on a schedule.

Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.