Budget variance, formula for a variance and favourable variance.
What you need to know
Answer each one before you reveal it.
State the formula for a variance.
Define a favourable variance.
Questions from this subtopic
Each one with the model answer underneath.
- 1
Define a budget variance.
Model answer
A budget variance is the difference between a budgeted figure and the actual figure achieved for the same item.
- 2
State the formula for a variance.
Model answer
Variance = actual figure − budgeted figure, described as favourable or adverse according to its effect on profit.
- 3
Define a favourable variance.
Model answer
A favourable variance is one that increases profit above the budgeted level, such as higher revenue or lower costs than planned.
- 4
Define an adverse variance.
Model answer
An adverse variance is one that reduces profit below the budgeted level, such as lower revenue or higher costs than planned.
- 5
Budgeted sales revenue is £250,000 and actual revenue is £268,000. Calculate the variance and state whether it is favourable or adverse.
Model answer
The variance is £18,000 favourable, because revenue is higher than planned.
- 6
Budgeted costs are £180,000 and actual costs are £192,000. Calculate the variance and state whether it is favourable or adverse.
Model answer
The variance is £12,000 adverse, because costs are higher than planned.
Other ways to work this
The same content, four other ways.
Everything in your subscription
Runs, plus a mode for every other kind of session.
Every question in Business Analysis and Decision-Making, on a schedule.
Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.