levo

The Development Project: Analysis and Design

Scheduling the project with a Gantt chart

  • 3 things to know
  • A2 Unit 2
Start revising · £5/month

Overview

Gantt chart, slack in a schedule and critical path.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What is a Gantt chart?

Key term

What is shown on each axis of a Gantt chart?

Key term

How is a dependency between two tasks shown on a Gantt chart?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is a Gantt chart?

    Model answer

    A Gantt chart is a horizontal bar chart of a project's tasks against time. Each task is one bar whose left edge is its start date and whose length is its duration, so the whole schedule can be read at a glance.

  2. 2

    What is shown on each axis of a Gantt chart?

    Model answer

    The vertical axis lists the tasks in the order they begin, and the horizontal axis is a timeline in days or weeks.

  3. 3

    How is a dependency between two tasks shown on a Gantt chart?

    Model answer

    A dependency is drawn as an arrow from the end of the earlier task to the start of the later one, showing that the second cannot begin until the first has finished.

  4. 4

    What is a milestone on a Gantt chart?

    Model answer

    A milestone is a point of zero duration marking the completion of a stage, drawn as a diamond rather than a bar. Signing off the requirements or delivering the tested system are typical milestones.

  5. 5

    How does a Gantt chart show that two tasks run at the same time?

    Model answer

    Two bars that overlap horizontally occupy the same span of the timeline, which shows the tasks are worked on concurrently. Testing one module while coding the next is shown this way.

  6. 6

    Why is a schedule broken into tasks before it is drawn?

    Model answer

    Breaking the work down forces every activity to be identified and given a duration, which exposes work that would otherwise be forgotten and makes the total estimate the sum of considered parts rather than a guess.

Other ways to work this

The same content, four other ways.

Everything in your subscription

Runs, plus a mode for every other kind of session.

1Flash
2Imposter
3Fade
4Brain dump

Learn every subtopic in runs of four questions

Facts flash and fade, a wrong word hides in some of them, and a brain dump decides which questions are locked in.

Systems Analysis and Development Approaches
Design, Development and Testing
Implementation and System Security
Programming

Cram the night before, weakest topic first

A quick scan finds your weakest topics. Recall each fact you missed three times in a row.

A check requires a value.
presencerangeformat

Blank Blitz consolidates the facts

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

✓What it iscovered
~Why it happenspartly there
How long it lastsnot there yet

Explain It tests your understanding

Explain a concept in your own words and see which of its points you covered.

One byte is made up of 8 bits.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The faults are the mistakes students make most often.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in The Development Project: Analysis and Design, on a schedule.

Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.