Finding the longest chain of dependent tasks, what total float and free float each mean, why a task on the critical path has none, and what happens when a task overruns its float.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

How is the critical path through a project plan identified?

Key term

A plan has two chains between the same two points, one of 20 days and one of 14 days. Which chain is critical?

Key term

What does it mean to say a task has zero float?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    How is the critical path through a project plan identified?

    Model answer

    The critical path is the longest chain of dependent tasks through the plan. Its length sets the earliest possible finish date.

  2. 2

    A plan has two chains between the same two points, one of 20 days and one of 14 days. Which chain is critical?

    Model answer

    The chain of 20 days is critical, because the development cannot finish before its longest chain of dependent work is complete.

  3. 3

    A critical chain runs for 20 days and a parallel chain between the same points runs for 14 days. How much float has the shorter chain?

    Model answer

    The shorter chain has six days of float, because 20 days minus 14 days leaves six spare days.

  4. 4

    What does it mean to say a task has zero float?

    Model answer

    A task with zero float cannot slip by even one day without delaying the finish of the whole development.

  5. 5

    Why does the developer watch the tasks on the critical path most closely?

    Model answer

    Delay to a critical task delays the delivery date, while delay elsewhere may be absorbed by the float on that task.

  6. 6

    What happens to the critical path when a task overruns more than its float?

    Model answer

    The overrunning task becomes critical, and the critical path shifts onto the chain that contains it.

Other ways to work this

The same content, four other ways.

Everything in your subscription

Runs, plus a mode for every other kind of session.

1Flash
2Imposter
3Fade
4Brain dump

Learn every subtopic in runs of four questions

Facts flash and fade, a wrong word hides in some of them, and a brain dump decides which questions are locked in.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram the night before, weakest topic first

A quick scan finds your weakest topics. Recall each fact you missed three times in a row.

A null is the of one.
absencepresencetype

Blank Blitz consolidates the facts

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

✓What it iscovered
~Why it happenspartly there
How long it lastsnot there yet

Explain It tests your understanding

Explain a concept in your own words and see which of its points you covered.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The faults are the mistakes students make most often.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Project Management and the Systems Approach in Practice, on a schedule.

Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.