CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Reasons for Systems Development and Systems Methodologies
Iterative, incremental and spiral development
- 3 things to know
- A2 Unit 1
Overview
Iterative development, how iterative working reduces the cost of a misunderstood requirement and regression risk created by repeatedly changing a partly built system.
What you need to know
Answer each one before you reveal it.
Distinguish iterative development from incremental development.
What makes the spiral model risk-driven?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What does iterative development mean?
Model answer
Iterative development means building a rough version of the system and then repeatedly refining it, so that analysis, design, coding and testing are revisited in each cycle rather than done once.
- 2
Distinguish iterative development from incremental development.
Model answer
Iterative development improves the same partial system over successive cycles until it is right, while incremental development delivers finished, usable slices of functionality one after another.
- 3
What is a timebox?
Model answer
A timebox is a fixed period of time set aside for a piece of work whose end date cannot be moved, so that if the work will not fit, the content is reduced rather than the deadline.
- 4
If a timebox is running short of time, what gives way, and how is the decision made?
Model answer
When a timebox runs short the agreed functionality gives way, and the decision is made by dropping the lowest-priority items first using a priority list agreed with the user before the timebox started.
- 5
Describe the four activities that make up one loop of the spiral model.
Model answer
One loop of the spiral model determines the objectives and constraints for that pass, identifies and resolves the main risks, develops and tests that portion of the system, and then plans the next loop with the customer.
- 6
What makes the spiral model risk-driven?
Model answer
The spiral model is risk-driven because the greatest remaining risk decides what is built next, so an unproven algorithm or an untested interface is prototyped early rather than left until the end.
Other ways to work this
The same content, four other ways.
Everything in your subscription
Runs, plus a mode for every other kind of session.
Every question in Reasons for Systems Development and Systems Methodologies, on a schedule.
Learn it in runs of four questions, each ending on a brain dump against the clock. Every question you lock in comes back the next day, then at longer gaps, each time just before you would forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.